For the assembly of an STS crane jacking system, our client needed an assembly team to install the system safely.
The system arrived in 40- 40Ft containers. The full installation of the system is to be completed within four weeks.
The work scope.
– Unload the containers;
– Unpack the containers;
– Installation of the sand bed for the jacking system base;
– Installation of the jacking system according to client requirements; and
– Commissioning the jacking system and handover to the jacking team
STARKON supplied required resources, such as manpower, tools and know-how. STARKON to ensure the correct installation of critical joint applications.
The project was completed within the scheduled time and with all client’s demands met. The project met all STARKON safety targets.