For the assembly of an STS crane jacking system, our client needed an assembly team to install the system safely.
The system arrived in 40- 40Ft containers. The full installation of the system is to be completed within four weeks.
The work scope.
– Unload the containers;
– Unpack the containers;
– Installation of the sand bed for the jacking system base;
– Installation of the jacking system according to client requirements; and
– Commissioning the jacking system and handover to the jacking team
We are always available to explain the solutions that we provide. For any particular problem causing operational issues or delays and which requires urgent action, please feel free to contact us at any time.